Concrete barriers blocking Ponce bike lane to be corrected 'within a month,' GDOT says
Yeah, that's not supposed to be there
Bicyclists pedaling on Ponce de Leon Avenue know to expect obstacles. Motorists will pull out in front of them or swerve out of their lanes. Pedestrians will sometimes step out into the street without looking. It's a busy road and you have to be careful.
Over the weekend, bicyclists encountered a new hazard near Ponce City Market.
Last Thursday, Georgia Department of Transportation work crews installed a large concrete median at the Ponce entrance to the mixed-use development and across the street at Midtown Place, the mammoth retail strip that includes Whole Foods, Home Depot, and an assortment of shops.
According to a GDOT Spokeswoman Annalysce Baker, the entrances to both developments are supposed to be "right-in, right-out." Motorists haven't respected this. The illegal left turns into the developments from the center lane of Ponce were causing logjams.
GDOT's concrete medians — Baker says they cost $900 apiece — were supposed to solve this dilemma. The only problem: the barrier at the PCM entrance was built on top of a bicycle lane, meaning that people pedaling east on Ponce would have to swerve into traffic or into PCM's driveway to avoid the barriers. Bicyclists raised holy hell and rightly so.
The Atlanta Bicycle Coalition is urging supporters to let GDOT know how they feel about the mix-up and to demand the agency to quickly address the issue.
Baker says GDOT is meeting with the contractor next week and "the issue will be corrected within a month."
Baker says GDOT, which identified the problem "as soon as it was poured by the contractor," will move the medians to "ensure that there is no conflict with the bike lane."
"We are working on plan modifications to reconstruct the median to make it narrower, lower islands with a sloped curb face," Baker says in an email. "Striping will also be changed to ensure cyclists can move safely and efficiently through the intersection. The Georgia DOT resurfaced and restriped the Ponce de Leon a few years ago to accommodate all communities who use Ponce de Leon including cyclists. The Georgia DOT ensures all communities who use the roadway will be accommodated."
Baker says the medians are one part of a $2.7 million "safety project" along the segment of Ponce between Moreland and Piedmont avenues that will include "upgrading pedestrian signal heads, sidewalks installation, and installing pedestrian beacons along the corridor."
Baker included two documents, one of which shows what she says is the original plan to add the median at the driveway.
"You will also see in the plans the restriping for the bike lanes to go behind the median, avoiding conflict," she writes. "You’ll see an oblong diamond with lines through it. That is the hatching or restriping that section of the two-way left turn lane to indicate to motorists traveling west on Ponce de Leon that a left turn in the driveway is not permitted."
embed-2
The second set of plans shows the planned pedestrian beacon crossing on Ponce near Somerset Terrace.